Question 1
A SAFe portfolio asks for capacity by role during a scenario. Which prerequisite must be true first?
Explanation
Role-based capacity requires attributes enabled and primary values populated to avoid double counting. Archiving scenarios or stripping stakeholders breaks planning, not enables it.
Question 2
A huge red bubble sits bottom-right on the workbench. How should leadership read it?
Explanation
Color and quadrant encode value/risk posture; red lower-right is the re-evaluate pocket. Green upper-left is the desirable opposite profile.
Question 3
Marking a rate type inactive does what for new time entry?
Explanation
Inactive types remain on old rows but disappear from new pick lists; processing may fall back to system rates when cards no longer match.
Question 4
Which SPM practice supports compliance when SAFe governance demands separation of duties?
Explanation
SoD is enforced through deliberate role boundaries across portfolio, demand, and planning personas—not blanket super roles.
Question 5
Which activity is intentionally supported from both Project Workspace and the Resource Management Workspace (with the right roles)?
Explanation
Assignment edits can originate in either workspace for qualified roles. Portfolio export is limited to the RM workspace UI, and installation tasks are administrative, not dual-surface features.