ServiceNow CIS-PPM and CIS-SPM - Project Portfolio Strategic Portfolio Management - Planning Governance Resources

By Marcus Chen · Updated May 25, 2026

Questions25
Passing Score75%
Format100% Multiple Choice
Sessions Logged1,704
Your progressLog in / Register to track times taken, best score, questions mastered, and coverage on this quiz.
Rating
Community rating 4.5 out of 5 from 15 ratings.
4.5 (15)

Topics covered

This quiz

Uncategorized25 (100%)

Uncategorized25 questions

Question catalog for this preview

Catalog listing of the 5 preview questions for this quiz.

Question 1

A project manager is tracking a construction project with dependencies: Task B cannot start until Task A is complete, and Task C cannot start until both Task A and Task B are complete. If Task A is delayed by 3 days, how should ServiceNow PPM automatically handle this?

Answer choices

  • A. The project manager manually updates all downstream task dates

  • B. ServiceNow PPM automatically recalculates the project schedule — Task B's start date shifts by 3 days (Finish-to-Start dependency), and Task C's start date shifts to accommodate both delayed predecessors; the project end date is updated; the critical path is recalculated to show schedule impact

  • C. Dependencies are informational only; dates don't update automatically

  • D. Create separate projects for each task to avoid dependencies

Question 2

A company's SPM governance board wants to implement a formal stage-gate review process for all major IT investments, inspired by Phase-Gate Management (Cooper's Stage-Gate model). Projects must pass through Gates: Gate 1 (Idea Screen), Gate 2 (Second Screen), Gate 3 (Decision to Develop), Gate 4 (Post-Development Review), Gate 5 (Launch/Implement). How does ServiceNow SPM/PPM configure this?

Answer choices

  • A. Create one approval step at the beginning of each project

  • B. Configure Phase Gates in SPM — define 5 gate records with: required deliverables checklist for each gate, designated gate keeper(s) for approval, evaluation criteria (must-meet and should-meet), scoring model; the investment/project can only advance through each gate with gate keeper approval

  • C. Allow all projects to proceed without gates to move faster

  • D. Gates are informational checkpoints only; they don't block project progression

Question 3

A project manager needs to track that a critical project milestone — "System Integration Testing Complete" — has been achieved before the project can move to User Acceptance Testing. If the milestone is missed, the project plan should be flagged and the sponsor notified. How is this configured in ServiceNow PPM?

Answer choices

  • A. Add a work note to the project when the milestone is complete

  • B. Create a Milestone task in the project plan; configure a business rule or Flow Designer trigger that fires when the milestone's planned date passes without completion — auto-generates a Project Status flag (Orange/Red), updates project health, and notifies the project sponsor

  • C. Rely on the project manager to remember milestone dates

  • D. Create separate Change Requests for each milestone

Question 4

A company wants to implement IT Financial Management alongside PPM — specifically, they want to track the total cost of each project (labor + tools + licenses) and show the actual cost vs. budget on project dashboards. How should this be configured in ServiceNow?

Answer choices

  • A. Finance tracks costs in ERP; project managers manually calculate separately

  • B. Configure IT Financial Management in ServiceNow — resource rates defined per role, actual time logged against projects generates labor cost calculations; direct costs and vendor invoices logged as project expenses; budget vs. actual cost comparison shown on the Project Finance tab

  • C. Only track labor hours, not monetary costs

  • D. Use a separate financial system and don't integrate with PPM

Question 5

A company's PMO wants to identify projects that are consistently over budget, behind schedule, or at risk of cancellation across a portfolio of 200 active projects. Instead of reviewing each project individually, they want automated identification of troubled projects. What SPM/PPM capability enables this?

Answer choices

  • A. PMO managers review all 200 projects weekly in meetings

  • B. Portfolio Health Scoring and Exception Reporting — configure health score thresholds (CPI < 0.8 = Red, SPI < 0.8 = Red); projects that cross thresholds are automatically flagged on the PMO Dashboard; the PMO can subscribe to automated alerts when projects change health status

  • C. Create a scheduled report emailed on Friday afternoons

  • D. Review only the top 10 largest projects by budget